Grid connection
Adding a battery to an existing solar install can trip a G98 system into G99 territory, and that changes the paperwork
Grid Guru's August 2026 newsletter says a battery can still go through as G98 if combined inverter capacity stays at or under 16 A per phase (3.68 kW single-phase), but adding an AC-coupled battery with its own 3.6 kW inverter to an existing 3.68 kW system means the whole installation needs a G99, approved before you install.
20 August 2026 · Source: Grid Guru
Adding storage to a Herne Bay solar installation is not always as simple as the original install. Grid Guru's August 2026 newsletter takes an installer's question about adding a battery to a solar system fitted under G98. It says the answer depends on the site's total generation capacity after the addition, because a battery that can export counts as generation. If the combined inverter capacity stays at or under 16 A per phase (3.68 kW single-phase), it can still go through as G98.
Add an AC-coupled battery with its own 3.6 kW inverter to an existing 3.68 kW system and you are over, and the whole installation needs a G99, approved before you install.
It describes two ways to keep things simple. A DC-coupled battery behind the existing hybrid inverter that does not raise the site's export capacity usually leaves the original notification standing, though you should check whether the DNO wants the storage unit logged. Or you can fit a G100-compliant export-limitation scheme to cap the site at its approved level.
Anyone in Herne Bay planning to add a battery should ask how it will be connected and whether a new DNO application is needed. We have summarised Grid Guru's newsletter here; your installer and network operator confirm what applies to your system.
Read the original: Grid Guru. Commentary is Herne Bay Solar's own editorial view; the original reporting is credited to its publisher.
More solar news
- British Gas closed its 15.1p Export & Earn Plus SEG tariff on 6 July; its page now lists 12p and 8p
- Plug-in solar regulations came into force on 27 August 2026: an 800W definition and a product specification
- SEG export rates run from 2p to 25p per kWh, and the highest rates come with strings attached
- 0% VAT on home solar and batteries is due to end on 31 March 2027, rising to 5%